Designing A Voice Recognition System For Tourists In Australia – Project Schedule And Cost Estimation Plan

Project Scope

The project is proposed for designing the voice recognition system to facilitate the tourists from the global world so that the immigration rate of tourist activity increases in the Australia. The Australian tourist board is looking forward to enhance the GDP of the nation to manage economic stability of the country. The development of the voice recognition system is proposed to increase the number of tourist families in the Australia. In the current year, the number of family visited Australia are 2,000,000. The purpose of this paper is to prepare a project schedule and cost estimation plan to analyse the profit earned by the country with the innovative structure of tourist online application.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The aim of this paper is to design and implement the voice recognition system to facilitates the tourist in making their tourist plan for visiting Australia.

The scope of the project is rely on the development of the project schedule, work breakdown structure, and cost breakdown structure to evaluate the cost benefit earned by the country with the deployment of innovative idea of voice recognition system in the working curriculum of the tourist websites.

  • Efficient and skilled staff
  • Suppliers supplies the resources on time
  • Coordination between the team members (Kaziliunas, 2012)
  • Approved budget of the project
  • Approved scheduled time of the project
  • Internet connectivity for communication 

The voice recognition system is the new technology implemented for guiding the tourist to make their plan easily (Raid, Sacha, Ritchie, and Brent, 2014). The queries forwarded by the customers are instantly solved with the help of voice messenger. The tourist get attracted towards newly designed website with the help of artificial intelligence concept.

Resources

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Cost ($)

Project Manager

15000

Risks Manager

40000

Technical Manager

23000

Project Designer

37000

System analyst

22000

Project quality manager

18000

Financial Manager

25000

Project Sponsors

25000

Procurement manager

15000

Activities

Cost

Gap analysis

85200

New plan proposal

85200

Selection of Stakeholder

142000

Project charter preparation

8000

Project charter approved

56800

Stakeholder Sign off

28400

Requirement specification

13440

Feasibility analysis

10400

Project schedule

4800

Resource management plan

7200

Cost estimation plan

7200

Installation program design

14000

Communication plan

6240

Resources

4800

Evaluation of project performance

23600

Cost benefit analysis

7200

Preparation of test plan and procedures

20760

System Testing

9040

Evaluating project success

64400

Network Implementation

12240

Network connection

21600

System Handover

113600

Operational Handover

56800

Closure Report

26000

Monitoring Operation

56800

Continuous improvement and change management plan

56800

Total cost

942,520

Activities

Sub-activities

Duration

Planning

Gap analysis

3

New plan proposal

3

Selection of Stakeholder

5

Project charter preparation

2

Project charter approved

2

Stakeholder Sign off

1

Feasibility analysis

Requirement specification

3

Feasibility analysis

5

Project schedule

2

Resource management plan

3

Cost estimation plan

3

Designing phase

Installation program design

7

Communication plan

3

Resources

2

Evaluation phase

Evaluation of project performance

5

Cost benefit analysis

3

Testing phase

Preparation of test plan and procedures

3

System Testing

2

Evaluating project success

2

Implementation phase

Network Implementation

3

Network connection

5

Closure phase

System Handover

4

Operational Handover

2

Closure Report

1

Monitoring Operation

2

Continuous improvement and change management plan

2

Total Duration

78 days

The cost estimation plan helps in analysing the variation in the cost due to the change in the market price during the actual set up of the project. The profitability of the Australian government will be increased due to the increasing number of tourist activities (Raz, Shenhar, and Dvir, D2011). The attraction point is the tourist guide which is a voice recognition system. The management of resources among the project team members helps in completing the project within the approved budget. The cost parameters are associate with each activity so that the difference in the estimated cost and actual cost can be minimized and results in increasing the net profit earned by the project. 

It is recommended to make use of Project management body of knowedge because it focuses on establishing interconnection and coordination between the 10 knowledge areas of the project. The proper scheduling of the processes of the knowledge areas helps in completing the project within assured time and cost.

Knowledge Areas

Description

Project integration management

Focuses on developing:

Project charter for approval of the project requirement

Project schedule (Patanakul, 2010)

Project control policies

Project change control policies

Project scope management

Requirement gathering

In-scope activities

Out-of-scope activities

Work breakdown structure

Cost breakdown structure

Verification and validation control

Project schedule management

Duration of time

Resource allocation

Systematic arrangement of activities

Control procedures

 Analysis of critical activities (Oliveira, Espindola, and Marins, 2014)

Project quality management

Determining required quality

Develops quality standards and control

Managing quality procedures

Project cost management

Estimation of project activities cost

Cost breakdown structure

Project resource management

Selection of project team

Categorisation of project team

Distribution of role and responsibilities

Accompanied with required control authorities

Project communication management

Communication tools

Flow of communication

Frequency

Message delivered

Project risks management

Risk matrix

Risk identification

Risks severity

Risks probability

Risks Ranking

Risks Impact

Risks management plan

Control measures

Monitoring of risks

Project procurement management

Resource requirement plan

Estimation of resource cost

Approval of procurement plan

Project Stakeholder management

Selection of the stakeholder

Communication tool

Stakeholder engagement plan

Project Schedule

The implementation of the project schedule helps in analysing the success parameters of the project (National Learning consortium, 2011). The cost and time breakdown structure should be reviewed to analyse the variation in the completion of project activities (Hans, 2013).

Time Breakdown structure

Activities

Sub-activities

Duration

Start date

Finish Date

Status

Planning

Gap analysis

3

10-10-18

12-10-18

In-process

New plan proposal

3

15-10-18

17-10-18

In-process

Selection of Stakeholder

5

18-10-18

24-10-18

In-process

Project charter preparation

2

25-10-18

26-10-18

In-process

Project charter approved

2

29-10-18

30-10-18

In-process

Stakeholder Sign off

1

31-10-18

31-10-18

In-process

Feasibility analysis

Requirement specification

3

1-11-18

5-11-18

In-process

Feasibility analysis

5

6-11-18

12-11-18

In-process

Project schedule

2

13-11-18

14-11-18

In-process

Resource management plan

3

15-11-18

19-11-18

In-process

Cost estimation plan

3

20-11-18

22-11-18

In-process

Designing phase

Installation program design

7

23-11-18

3-12-18

In-process

Communication plan

3

4-12-18

6-12-18

In-process

Resources

2

7-12-18

10-12-18

In-process

Evaluation phase

Evaluation of project performance

5

11-12-18

17-12-18

In-process

Cost benefit analysis

3

18-12-18

20-12-18

In-process

Testing phase

Preparation of test plan and procedures

3

21-12-18

25-12-18

In-process

System Testing

2

26-12-18

27-12-18

In-process

Evaluating project success

2

28-12-18

31-12-18

In-process

Implementation phase

Network Implementation

3

1-1-19

3-1-19

In-process

Network connection

5

4-1-19

10-1-19

In-process

Closure phase

System Handover

4

11-1-19

16-1-19

In-process

Operational Handover

2

17-1-19

18-1-19

In-process

Closure Report

1

21-1-19

21-1-19-

In-process

Monitoring Operation

2

22-1-19

23-1-19

In-process

Continuous improvement and change management plan

2

24-1-19

25-1-19

In-process

Total Duration

78 days

In-process

From the cost breakdown structure, it can be analysed that the project is completed successfully within the approved cost for the project development cycle.

Activities

Estimated Cost ($)

Actual cost

Gap analysis

85200

82300

New plan proposal

85200

86000

Selection of Stakeholder

142000

145678

Project charter preparation

8000

6800

Project charter approved

56800

55478

Stakeholder Sign off

28400

29800

Requirement specification

13440

13440

Feasibility analysis

10400

11000

Project schedule

4800

4325

Resource management plan

7200

7189

Cost estimation plan

7200

7340

Installation program design

14000

15000

Communication plan

6240

6453

Resources

4800

5670

Evaluation of project performance

23600

22567

Cost benefit analysis

7200

7100

Preparation of test plan and procedures

20760

20765

System Testing

9040

8000

Evaluating project success

64400

64500

Network Implementation

12240

12345

Network connection

21600

22900

System Handover

113600

113245

Operational Handover

56800

56777

Closure Report

26000

25000

Monitoring Operation

56800

57888

Continuous improvement and change management plan

56800

53000

Total cost

942,520

940560

Resource allocation to the project activities:

Activities

Resources

Gap analysis

Project Manager

Project Sponsor

New plan proposal

Project Manager

Project Sponsor

Selection of Stakeholder

Project Manager

Project Sponsor

Project charter preparation

Project Manager

Project Sponsor

Project charter approved

Project Manager

Project Sponsor

Stakeholder Sign off

Project Manager

Requirement specification

System Designer

Feasibility analysis

Project Manager

Project schedule

Project Manager

Resource management plan

Project Manager

Cost estimation plan

Technical manager

Installation program design

System Designer

Communication plan

Project Manager

Resources

Project Manager

Evaluation of project performance

Project Manager

Cost benefit analysis

Project Manager

Preparation of test plan and procedures

Project Manager

System Designer

System Testing

System analyst

Quality manager

Evaluating project success

Project Manager

Network Implementation

System Designer

Network connection

System Designer

System Handover

Project Manager

Project Sponsor

Operational Handover

Project Manager

Project Sponsor

Closure Report

Project sponsor

Monitoring Operation

Project Manager

Continuous improvement and change management plan

Project Manager

The post implementation plan is developed for improving the performance of the project by analysing the gaps and flaws occurred in estimated cost, time, quality, and control. The review of the implementation plan is summarised below in the table:

Findings

Description

Time Management plan

The successful deployment of the project schedule helps in completing the project on the scheduled date of 25 Jan, 2019.

Variance: The variance in the scheduled date of implementation will not occur

Cost Estimation plan

The project is completed within the estimated cost of the project

Variance: The variance between the estimated cost and actual cost is $ 1960

Project Methodology

The identification of specific process in the knowledge areas of the PMBOK process group helps in completing the project according to the goal and objectives (Munns, and Bjeirmi, 2012)

Variance: Not occur

Goal

Improved migration of tourist with the development of voice recognition system

Variance: The goal is successfully achieved

Resource distribution

Resources are effectively distributed among the stakeholder as required (Koskela, and Howell, 2014)

Variance: Not Occur

  • Development of the quality standards for the project control
  • Analysing the flaws and gaps of the existing structure
  • Analyse voice of customers
  • Identify the areas of improvement
  • Identify the root cause analysis of the project variation (Mansfield community, 2013)
  • Final upgrading of the project areas of improvement
  • Pilot testing of the project
  • Evaluation of the test result
  • Monitoring the project progress

Conclusion

It can be concluded that the cost estimation plan helps in analysing the variation in the cost due to the change in the market price during the actual set up of the project. The identification of specific process in the knowledge areas of the PMBOK process group helps in completing the project according to the goal and objectives

References 

Hans, R. (2013). Work Breakdown Structure: A tool for software project scope verification. 1st ed. [ebook] online. Available at: https://airccse.org/journal/ijsea/papers/4413ijsea02.pdf[Accessed 28 Sep. 2018].

Kaziliunas, A. (2012). Problems while implementing quality management system for a sustainable development of organization (1st ed.). 1st ed. [ebook] online. Available at: https://www.su.lt/bylos/mokslo_leidiniai/ekonomika/2012_4_28/kaziliunas.pdf [Accessed 28 Sep. 2018].

Koskela, L., and Howell, G. (2014). Reforming project management: The role of planning, execution, and controlling. 1st ed. [ebook]. Available at: https://pdfs.semanticscholar.org/10be/3cbd41cd844986ac7a5293a901303cea16ef.pdf [Accessed 28 Sep. 2018].

Mansfield Community. (2013). Introduction to project management. 1st ed. [ebook]. Available at: https://www.mansfield.vic.gov.au/Libraries/Community_Development/Intro_to_Project_Management_Manual.sflb.ashx [Accessed 28 Sep. 2018].

Munns, A., and Bjeirmi, B. (2012). The role of project management in achieving project success. 1st ed. [ebook] online. Available at: https://notendur.hi.is/vio1/The_role_of_project_management_in_achieving_project_success.pdf [Accessed 28 Sep. 2018].

National Learning consortium. (2011). Continuous quality improvement strategies to optimize your practice. 1st ed. [ebook]online. Available at: https://www.healthit.gov/sites/default/files/nlc_continuousqualityimprovementprimer.pdf [Accessed 28 Sep. 2018].

Oliveira, U., Espindola, L., and Marins, F. (2014). Analysis of supply chain risks management researches. 1st ed. [ebook]. Available at: https://www.scielo.br/pdf/gp/2017nahead/en_0104-530X-gp-0104-530X3515-16.pdf [Accessed 28 Sep. 2018].

Patanakul, P. (2010). An Empirical study on the use of project management tools and techniques across project life cycle and their impact on project success. Ebook [Online]. Available at: https://www.researchgate.net/publication/260059419_An_Empirical_Study_on_the_use_of_Project_Management_Tools_and_Techniques_across_Project_Life-Cycle_and_their_Impact_on_Project_Success[Accessed on Sep 16, 2018]

Raid, Sacha, Ritchie, and Brent. (2014). Risk Management: Event Manager’s attitude, Beliefs, and Percieved constraints. 1st ed. [ebook]. Available at: https://research-repository.griffith.edu.au/bitstream/handle/10072/42679/71469_1.pdf?sequence=1&isAllowed=y [Accessed 28 Sep. 2018].

Raz, T., Shenhar, A., and Dvir, D. (2011). Risk Management, project success, and technological uncertainty. 1st ebook. Available at: https://www.researchgate.net/publication/227644860_Risk_Management_Project_Success_and_Technological_Uncertainty. [Accessed on Sep 16, 2018]