Implementation Of 2 New Servers And 10 Computers For Small Organization

Objectives of the Proposal

The project had been developed for the arrangement of the two servers and 10 computer devices for an organization. The implementation of the networking server would require the effective and smart planning as there are numerous requirements for the implementation of the network servers and computer devices for the small organization. The problems that need to be sorted in the operations of the project are lack of the dedicated server for the storage media of the small organization.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The development of the 2 servers and the installation of the 10 computers would ensure that the small organization would be able to carry out their business and operations. The implementation of the improved processes would be resulted from the installation of the servers and connecting them on a mass scale. The support of the improvement strategies would lead to the benefit of the organization in managing and maintaining their operations with the help of server and network connection. It would enhance the scope for the improvement of the operations of the organization and development of the operations.

The implication of the 2 servers and 10 computers at the work station would help in forming the improved operations for the organization. The execution of the enhanced procedures would be come about because of the establishment of the servers and interfacing them on a mass scale. The help of the change methodologies would prompt the advantage of the association in overseeing and keeping up their operations with the assistance of server and system association. It would upgrade the degree for the change of the operations of the association and improvement of the operations.

The performance measurement of the implemented network with 2 servers and 10 computers installed at the main workstation. The development of the improved processes would be measured in terms of the effectiveness of the operations of the organization. The time taken for running a query (data transfer, copy or modification) would be considered for evaluation of the performance. The measurement of the performance is also done for realizing the improvement of the existing facilities and formation of the improved processes.

The project is IT based and involves the development of the effective operations for the organization to carry out its data management and storage. The project requires the use of market analytics for the development of the improved technological tools and equipments. However, the project can be considered as the technological development of the small organization and it would serve the purpose of improved processes and market analysis too. The data collected and evaluated would help the organization for improving their existing facilities by implementing improved operations.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Performance Measurement

There are several small organizations and companies that require the use of server based operations for increasing their efficiencies and developing improved processes in the organization. The management of the improved processes would form the implementation of the organizational development. The support of the improvement strategies would lead to the benefit of the organization in managing and maintaining their operations with the help of server and network connection. It would enhance the scope for the improvement of the operations of the organization and development of the operations.

The development of the project of the Implementation of the 2 new servers and 10 new computer devices would result in forming the accurate and systematic development of the organization. The project can be considered as the technological development of the small organization and it would serve the purpose of improved processes and market analysis too. The expansion of the market of the organization would be resulted by the deployment of the servers and new computers. The development of the organization had resulted in forming the occasional influence on the development of the operations. The increase of the customers and scalable expansion of market would be caused by the use of the project planning and execution.

The specific target of the project is the IT development organizations and the small organizations that are in need of the existing facilities and development of operations. The increase of the customers would be resulted from the expansion of the existing operations and development of the improved functions for the organization.

The implementation of the two new servers is a matter of risk and the organization would have to deal with the issues like misalignment of the servers, issues of the system failure, threat of data loss, and cease of resources. These are the major issues or dis-benefit of the project including the depletion of the resources, time consuming for the completion of the operations and the excessive exhaustion of the resources.

There are some human as well as some material resources required for the completion of the project successfully. The most prior requirement of the project would be the funds and the money required for the accumulation of the other resources. The project manager, planner, analyst, network engineer, network designer, contractor, and workers are the human resources  and computer devices and network equipments are the material resources required for the project. The complete list is given below,

Expected Benefits and Market Analysis

Resource Name

Activities Involved in

Project Manager

Requirement Analysis

Approval of the documents

Reviewing the plan outline with requirements

Signed off

Project is closed

Project Planner

Analysis of the Requirements of the project

Developing outline for the plan

Making Complete plan for the project

Analyst

Developing Initial Documents

Making the Project Charter Documents

Submitting the initial documents and charter for approval

Final report is developed

Submitted for sign off

Network Designer

Completion of the design

Network Components are aligned as per design

Software and Tools are installed in the device

Programming is done

Testing of the network components are done

Contractor

Site Planning is Developed

Computer Devices are set up

Workers

Basic infrastructure is formed

Computer Devices are set up

Computer Devices

(Material Resources)

Computer Machines are purchased

Network Equipments

(Material Resources)

Network Routers and switches are installed

Network Engineer

Client’s requirement is considered

Network Components are considered for design

Structure and Design outlay are made

Evaluation of the Design

Completion of the design

The project is IT based and involves the development of the effective operations for the organization to carry out its data management and storage. The assumptions of the project are the listed below,

  • All resources of the project are available for utilization
  • Team Members would work properly and in harmony
  • Project schedule and resources are ample for completion of the project
  • Project would be completed in time
  • Completion of the project would help in developing improvement in the operations of the organization

The project is IT based and involves the development of the effective operations for the organization to carry out its data management and storage. The constraints of the project are listed below,

Time: The duration of the project acts as the primary constraint for the project as it is expected that the project would be completed within the time limit of 3 months

Budget: The project has an expected budget of $50,000.00 and it should be ensured that the complete project would complete in that amount of resources

Quality: The improvement of the operations of the project would serve the major constraint for the project as the successful completion would be dependent on the improvement of the operations

Task Name

Cost

Installation of 2 new servers and 10 computers in small business

$49,240.00

   Project Initialization

$5,280.00

      Requirement Analysis

$2,000.00

      Developing Initial Documents

$760.00

      Making the Project Charter Documents

$760.00

      Submitting the initial documents and charter for approval

$760.00

      Approval of the documents

$1,000.00

   Project Planning

$7,840.00

      Analysis of the Requirements of the project

$1,520.00

      Developing outline for the plan

$2,280.00

      Reviewing the plan outline with requirements

$1,000.00

      Making Complete plan for the project

$3,040.00

   Network Designing

$5,880.00

      Client’s requirement is considered

$840.00

      Network Components are considered for design

$1,680.00

      Structure and Design outlay are made

$2,520.00

      Evaluation of the Design

$840.00

      Completion of the design

$0.00

   Site Development

$17,360.00

      Site Planning is Developed

$3,200.00

      Basic infrastructure is formed

$8,800.00

      Computer Machines are purchased

$1,560.00

      Computer Devices are set up

$3,360.00

      Network Routers and switches are installed

$440.00

   Software Configuration

$9,600.00

      Network Components are aligned as per design

$2,880.00

      Software and Tools are installed in the device

$2,880.00

      Programming is done

$1,920.00

      Testing of the network components are done

$1,920.00

   Final Documentation and Closure

$3,280.00

      Final report is developed

$1,520.00

      Submitted for sign off

$760.00

      Signed off

$1,000.00

      Project is closed

$0.00

 The overall budget for the project is $50,000.00 AUD.

The overall cost and the main budget for the project had been calculated by the use of the Ms-project software. The basic assumption made for calculating the cost of each activities is by considering a minimum working rate and cost of the resources as,

Resource Name

Std. Rate

Project Manager

$125.00/hr

Planner

$95.00/hr

Analyst

$95.00/hr

Networking engineer

$120.00/hr

Contractor

$100.00/hr

Workers

$110.00/hr

Computer Devices

$1,560.00

Network Equipments

$440.00

Network Designer

$105.00/hr

Over budget: The over budget of the project would result in depletion of the excess resources in the project.

Delay in completion: It is possible that the overall project completion would take more time than expected for completion of the project.

Network Error: The network errors would result in causing the systematic incompatibility of the operations and the data stored.

Misalignment of the servers: The misalignment of the servers would result in causing the major issues of the organizational operations.

Data incompatible: The data used for the storage of the information of the organization might not be compatible with the storage of the new servers.

Risk

Description

Mitigation

Over budget

The over budget of the project would result in depletion of the excess resources in the project.

Provisional Budget should be made

Delay in completion

It is possible that the overall project completion would take more time than expected for completion of the project.

Proper Planning should be developed

Network Error

The network errors would result in causing the systematic incompatibility of the operations and the data stored.

The network connection should be tested by using prototype testing

Misalignment of the servers

The misalignment of the servers would result in causing the major issues of the organizational operations.

Server compatibility should be checked and reviewed

Data incompatible

The data used for the storage of the information of the organization might not be compatible with the storage of the new servers.

Backup data should be kept in case of data loss

WBS

Task Name

Duration

Start

Finish

0

Installation of 2 new servers and 10 computers in small business

50 days

Mon 10/2/17

Fri 12/8/17

1

   Project Initialization

5 days

Mon 10/2/17

Fri 10/6/17

1.1

      Requirement Analysis

2 days

Mon 10/2/17

Tue 10/3/17

1.2

      Developing Initial Documents

1 day

Wed 10/4/17

Wed 10/4/17

1.3

      Making the Project Charter Documents

1 day

Thu 10/5/17

Thu 10/5/17

1.4

      Submitting the initial documents and charter for approval

1 day

Fri 10/6/17

Fri 10/6/17

1.5

      Approval of the documents

1 day

Fri 10/6/17

Fri 10/6/17

2

   Project Planning

10 days

Mon 10/9/17

Fri 10/20/17

2.1

      Analysis of the Requirements of the project

2 days

Mon 10/9/17

Tue 10/10/17

2.2

      Developing outline for the plan

3 days

Wed 10/11/17

Fri 10/13/17

2.3

      Reviewing the plan outline with requirements

1 day

Mon 10/16/17

Mon 10/16/17

2.4

      Making Complete plan for the project

4 days

Tue 10/17/17

Fri 10/20/17

3

   Network Designing

7 days

Mon 10/23/17

Tue 10/31/17

3.1

      Client’s requirement is considered

1 day

Mon 10/23/17

Mon 10/23/17

3.2

      Network Components are considered for design

2 days

Tue 10/24/17

Wed 10/25/17

3.3

      Structure and Design outlay are made

3 days

Thu 10/26/17

Mon 10/30/17

3.4

      Evaluation of the Design

1 day

Tue 10/31/17

Tue 10/31/17

3.5

      Completion of the design

0 days

Tue 10/31/17

Tue 10/31/17

4

   Site Development

18 days

Wed 11/1/17

Fri 11/24/17

4.1

      Site Planning is Developed

4 days

Wed 11/1/17

Mon 11/6/17

4.2

      Basic infrastructure is formed

10 days

Tue 11/7/17

Mon 11/20/17

4.3

      Computer Machines are purchased

2 days

Tue 11/21/17

Wed 11/22/17

4.4

      Computer Devices are set up

2 days

Thu 11/23/17

Fri 11/24/17

4.5

      Network Routers and switches are installed

1 day

Tue 11/21/17

Tue 11/21/17

5

   Software Configuration

10 days

Wed 11/22/17

Tue 12/5/17

5.1

      Network Components are aligned as per design

3 days

Wed 11/22/17

Fri 11/24/17

5.2

      Software and Tools are installed in the device

3 days

Mon 11/27/17

Wed 11/29/17

5.3

      Programming is done

2 days

Thu 11/30/17

Fri 12/1/17

5.4

      Testing of the network components are done

2 days

Mon 12/4/17

Tue 12/5/17

6

   Final Documentation and Closure

3 days

Wed 12/6/17

Fri 12/8/17

6.1

      Final report is developed

2 days

Wed 12/6/17

Thu 12/7/17

6.2

      Submitted for sign off

1 day

Fri 12/8/17

Fri 12/8/17

6.3

      Signed off

1 day

Fri 12/8/17

Fri 12/8/17

6.4

      Project is closed

0 days

Fri 12/8/17

Fri 12/8/17

WBS

Task Name

Description

1

Project Initialization

The first phase of the project consists of requirement analysis, developing initial documents, making the project charter documents, submitting the initial documents and charter for approval, and approval of the documents

2

Project Planning

The phase consists of analysis of the requirements of the project, developing outline for the plan, reviewing the plan outline with requirements, and making complete plan for the project

3

Network Designing

The phase consists of client’s requirement is considered, network components are considered for design, structure and design outlay are made, evaluation of the design, and completion of the design

4

Site Development

The phase consists of site planning is developed, basic infrastructure is formed, computer machines are purchased, computer devices are set up, and network routers and switches are installed

5

Software Configuration

The phase consists of network components are aligned as per design, software and tools are installed in the device, programming is done, and testing of the network components are done

6

Final Documentation and Closure

The final phase consist of final report is developed, submitted for sign off, signed off, and project is closed

Conclusion

It can be concluded from the report that the project of implementation of the 2 servers and 10 computers would be formed for the development of the small organization and improvement of its operations. The project is IT based and involves the development of the effective operations for the organization to carry out its data management and storage. The use of networking concept and the project management concepts had helped in forming the completion of the project. The execution of the improved strategies would be occurred in light of the foundation of the servers and interfacing them on a mass scale. The assistance of the change philosophies would provoke the benefit of the relationship in supervising and keeping up their operations with the help of server and framework affiliation.

References

Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute.

Gido, J., Clements, J. and Clements, J., 2014. Successful project management. Nelson Education.

Heldman, K., 2015. PMP project management professional exam deluxe study guide: updated for the 2015 Exam. John Wiley & Sons.

Kerzner, H., 2013. Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Larson, E.W. and Gray, C., 2013. Project Management: The Managerial Process with MS Project. McGraw-Hill.

Leach, L.P., 2014. Critical chain project management. Artech House.

Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking project management performance and project success. International journal of project management, 32(2), pp.202-217.

Schwalbe, K., 2015. Information technology project management. Cengage Learning.

Turner, R., 2016. Gower handbook of project management. Routledge.

Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.

Walker, A., 2015. Project management in construction. John Wiley & Sons.