Project Charter For I-Crop Project: Mobile Application And Website Development

Purpose

The following assignment is a project charter document developed for integrating the analysis of the mobile application and website development for I-Crop project. The purpose of the charter is to form an initial requirement document for the stakeholders so that they can understand the project more easily.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The purpose of the report is to develop a project charter that can be used as an initial document containing all required documents for getting an overview of the mobile application and website development for I-Crop project.

The objectives of the report are,

  • To develop an initial document comprising of information about the project schedule and budgetary information
  • To enhance the management of the successful development by passing on the information to its stakeholders

The website and mobile application would be effectively helpful in managing the project objectives. The orders and services would be increased and managed easily with the help of the improved communication plan development.

The Globex has decided to implement a new mobile application and website development and named it ‘I-Crop Project’. It would help them in managing the customers and getting active feedbacks from their customer.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Social: The social media platform would be responsible for the development of the successful management of the activities and aligning the formation of the increased management operations. The utilization of the improved functional development would be helpful for aligning the completion of the activities.

Operational: The operational development would be implied for easing the management of the successful development of activities. It is largely responsible for the continuation of the activities and forming management of the functional development.

Customer: The customer focus on the website development for I-Crop project would be effectively aligned with the independent management of the activities. The customer involvement would be effectively deployed for listing the evaluation of the functions for taking care of actions.

Financial: The financial operations of the I-Crop project would be held responsible for the completion of the activities and aligning development model.

Better- the implementation of the I-Crop project would be effectively deployed for integrating the utilization and formation of the successful continuation of the projects.

Faster- the faster completion of the projects would be implied for forming the cohesive management of the activities.

Cheaper- the overall cost required for the completion of the activities of Globex can be reduced by the help of the automatic activities due to the I-Crop project.

Do more- the applications of I-Crop project would be implied for taking care of the prominent development of the operations like communication and information transfer.

1

Financial

Profit Margin

3

2

Customer

Feedbacks and Orders

4

3

Operational

Processing Time

2

4

Strategy

Effective Implication

1

5

Social

Feedbacks on social media web

5

In scope- The in scope items of the project of website and mobile application for I-Crop include the development of the project plan, initiation documents, design, website development, mobile application development, UX development, testing activities, and final documentation.

Out of scope- the out of scope items of the project include the transportation requirements, change management, and communication plan.

Assumptions- It has been assumed for the project of website and mobile application for I-Crop that,

  • Project would be completed in the estimated time and budget
  • Uses of the provident development factors can be implied for successful alignment development
  • Resources required for the completion of the project would be done cohesively

Constraints- the factors of time, budget, and resource usage are the primary constraints for the project of website and mobile application for I-Crop

Resources: Analyst, Application Designer, Application Developer, Documenter, Engineer, Planner, Programmer, Project Manager, Website Designer, and Website Developer

Project Description

Technology: Design Development, Mobile Application Development, Mobile Application UI Development, Testing technology, and Website Development

Facilities: UI simulation environment and Testing facility is required for the completion of the project of website and mobile application for I-Crop

WBS

Milestone Name

Duration

Start

Finish

1.5

Signing off

0 days

Fri 10/12/18

Fri 10/12/18

2.5

Approving Complete Plan

0 days

Mon 10/29/18

Mon 10/29/18

3.1.5

   Approving Website

0 days

Tue 11/13/18

Tue 11/13/18

3.2.5

   Approving Mobile Application

0 days

Wed 11/28/18

Wed 11/28/18

5.5

Closure

0 days

Thu 1/31/19

Thu 1/31/19

WBS

Task Name

1.1

      Analyzing requirements

1.2

      Making Project Charter Documents

1.3

      Making Project Initiation Documents

1.4

      Submitting documents

1.5

      Signing off

2

   Planning Phase

2.1

      Selecting Plan Methodology

2.2

      Making Plan Outline

2.3

      Reviewing Plan Outline

2.4

      Making Complete Plan

2.5

      Approving Complete Plan

3

   Designing Phase

3.1

      Website Designing

3.1.1

         Selecting Design Platform

3.1.2

         Making Website Outline

3.1.3

         Reviewing Website Outline

3.1.4

         Making Complete Website

3.1.5

         Approving Website

3.2

      Mobile Application Designing

3.2.1

         Selecting Design Platform

3.2.2

         Making Mobile Application Outline

3.2.3

         Reviewing Mobile Application Outline

3.2.4

         Making Complete Mobile Application

3.2.5

         Approving Mobile Application

4.1.1

         Buying Website Domain

4.1.2

         Developing Website Interface

4.1.3

         Aligning Functions of Website

4.1.4

         Making Programs for Website

4.1.5

         Checking Mobile Compatibility

4.1.6

         Completion of Website Development

4.2

      Mobile Application Development

4.2.1

         Developing Application Interface

4.2.2

         Making Programs for Mobile Application

4.2.3

         Integrating Mobile Applications

4.2.4

         Completion of Mobile Application Development

5

5.1

      Making Closure Reports

5.2

      Making Evaluation Checklist

5.3

      Submitting Report Documents

5.4

      Signing off

5.5

      Closure

                       

Estimates for Each Activity / Task

WBS

Task Name

Resource Names

Cost

 
 

1.1

      Analyzing requirements

Analyst

$160.00

1.2

      Making Project Charter Documents

Documenter,

Documents[1]

$1,735.00

1.3

      Making Project Initiation Documents

Documenter,

Documents[1]

$1,735.00

1.4

      Submitting documents

Documenter

$1,040.00

1.5

      Signing off

 

$0.00

2

   Planning Phase

 

$7,200.00

2.1

      Selecting Plan Methodology

Planner

$1,120.00

2.2

      Making Plan Outline

Planner

$1,680.00

2.3

      Reviewing Plan Outline

Project Manager

$2,160.00

2.4

      Making Complete Plan

Planner

$2,240.00

2.5

      Approving Complete Plan

 

$0.00

3

   Designing Phase

 

$25,760.00

 

3.1.1

         Selecting Design Platform

Website Designer,

Design Tools[1]

$3,400.00

3.1.2

         Making Website Outline

Website Designer

$2,400.00

3.1.3

         Reviewing Website Outline

Engineer

$2,080.00

3.1.4

         Making Complete Website

Website Designer,

Design Tools[1]

$5,000.00

3.1.5

         Approving Website

 

$0.00

3.2

      Mobile Application Designing

 

$12,880.00

3.2.1

         Selecting Design Platform

Application Designer,

Design Tools[1]

$3,400.00

3.2.2

         Making Mobile Application Outline

Application Designer

$2,400.00

3.2.3

         Reviewing Mobile Application Outline

Engineer

$2,080.00

3.2.4

         Making Complete Mobile Application

Application Designer,

Design Tools[1]

$5,000.00

3.2.5

         Approving Mobile Application

 

$0.00

 
 

4.1.1

         Buying Website Domain

Engineer,

Domain Cost[1]

$3,080.00

4.1.2

         Developing Website Interface

Website Developer

$3,520.00

4.1.3

         Aligning Functions of Website

Website Developer

$2,640.00

4.1.4

         Making Programs for Website

Programmer

$2,880.00

4.1.5

         Checking Mobile Compatibility

Website Developer

$1,760.00

4.1.6

         Completion of Website Development

Website Developer

$2,640.00

 

4.2.1

         Developing Application Interface

Application Developer

$2,640.00

4.2.2

         Making Programs for Mobile Application

Programmer

$5,760.00

4.2.3

         Integrating Mobile Applications

Engineer

$3,120.00

4.2.4

         Completion of Mobile Application Development

Application Developer

$6,160.00

 

5.1

      Making Closure Reports

Documenter, Documents[1]

$1,735.00

5.2

      Making Evaluation Checklist

Project Manager

$3,240.00

5.3

      Submitting Report Documents

Documenter

$1,040.00

5.4

      Signing off

Project Manager

$2,160.00

5.5

      Closure

 

$0.00

Resource Name

Work

Standard Rate

Cost

Analyst

16 hrs

$10.00/hr

$160.00

Documenter

104 hrs

$65.00/hr

$6,760.00

Planner

72 hrs

$70.00/hr

$5,040.00

Project Manager

56 hrs

$135.00/hr

$7,560.00

Website Designer

72 hrs

$100.00/hr

$7,200.00

Application Designer

72 hrs

$100.00/hr

$7,200.00

Engineer

72 hrs

$130.00/hr

$9,360.00

Website Developer

96 hrs

$110.00/hr

$10,560.00

Programmer

72 hrs

$120.00/hr

$8,640.00

Application Developer

80 hrs

$110.00/hr

$8,800.00

Documents

3

$175.00

$525.00

Design Tools

4

$1,800.00

$7,200.00

Domain Cost

1

$1,000.00

$1,000.00

Total Budget

$80,005.00

  • Project would be completed in the estimated budget
  • Uses of the resources have been done considering the alignment of functions.
  • Resources required for the completion of the project would be done cohesively

Delay in completion: It is resulted due to the major or minor problems in execution of the operations of project resulting in untimely completion of the project

Shortage of resources: It is resulted due to the lack of adequate resources in the project or due to misuses of the resources by the project team

Design flaws: It is resulted due to the flaws in the design of the website and mobile application that needed to be corrected by the designer

Functional errors: It is the issues in the website and mobile application due to the functions not working properly or programming errors

Human mistakes: It is the probable mistakes of minor type that is occurred by the project team members and results in forming issues in completion of the project

Risk Factor

Responsible Person

Probability

(1-5)

Impact

(1-5)

Rating

Probability*Impact

Delay in completion

Project Manager

5

2

10

Shortage of resources

HR Manager

3

3

9

Design flaws

Designer

2

4

8

Functional errors

Engineer

3

5

15

Human mistakes

Team Members

4

3

12

Verification Activities: The identification of the coding requirements, programming platform, and verification of the effective management.

Validation Activities: The correction of the bugs, go live functions, and phase development would be helpful for defining the role of successful integration and development.

Annotated Bibliography

Article: The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework

Journal: International Journal of Project Management

Author(s): Badewi, A.

Summary: According to Badewi (2016), the impact of project management and benefit management practices have been largely deployed for adjusting the analysis of the operations and defining of the successful management operations. The project management has been holding considerable role for the evaluation of the existing operations and aligning the imitation of the effective operations. The evaluation of the methodologies of development and execution had been largely employed for forming the management of the successive development. The combination of the practices of development had been implied for listing the management of the operations and definite increment of the successful project execution. The framework for the smart alignment model would be helpful for listing the evolution of the project management and alignment of the smart project execution. The analysis of the functions for benefit management and project management practices for the completion of the project structural framework.

Article: An empirical study into identifying project complexity management strategies

Journal: Procedia Engineering

Author(s): Kermanshachi, S., Dao, B., Shane, J., and Anderson, S.

Summary: According to Kermanshachi, Dao, Shane & Anderson (2016), the analysis of the complex project management is a major factor for defining the influence for the development modelling. The study was conducted for understanding the significance of the factors of project management and the utilization and development using the innovative and effective project management. The alignment of the probable management process for the listing of the contemporary management has been helpful for co-ordinating the development of the innovation and smart project development. The management of the complex projects would be aligned for implying the renovation development and implication of the innovative technology. The integration for the successive management would be implied for innovation the prospect of smart project development. The alignment of the successive introduction management would be implied for operations. The usefulness of the project integration development would be listed for aligning with the cohesive management development.

Project Details

Article: Key factors of sustainability in project management context: A survey exploring the project managers’ perspective

Journal: International Journal of Project Management

Author(s): Martens, M. L., and Carvalho, M. M.

Summary: As stated by Martens and Carvalho (2017), the key factors for the successful sustainability of the project management operations. The context of project management has been largely implied for listing the utilization of the smart innovation formation. The sustainability of the project activities had been largely responsible for innovation of the activities and integrating the alignment and development. The deployment would be aligned for successful integration and utilization of the factors for easing the management process. The integration and implication of the effective project management development would be helpful for innovating the consideration and development. The exploration of the activities for implying the management of the operations for the operational development of the operations has been implied for implying the successful development model. The identification of the key factors for using the successful integration and management activities was implied for innovation development. 

The project closure checklist is managed for the involvement of the improved management and development. The closure checklist would be accordingly developed considering the innovation and implication management. The following is the closure checklist for the project,

Checklist Item

Checked?

Is the project plan sustainable for the developing mobile application and website?

Right

Have all the initiation documents made successfully for alignment of activities?

Right

Are the outputs of design simulation positive for users?

Right

Is Program Development for the project aligned with the completion plan?

Right

Are the final project report been made cohesively?

Right

The evaluation of the project is aligned with the consideration and evaluation of the factors for integrating the successful innovation and development. The evaluation of the project integration and management can be implied for integrating the utilization and management process. The evaluation of the activities had been integrating the management process. The evaluation of the activities has been largely responsible for aligning management of the activities. The evaluation factors are,

  • Project plan sustainable for the developing mobile application and website
  • Initiation documents made successfully for alignment of activities
  • Outputs of design simulation positive for users
  • Program development for the project aligned with the completion plan
  • Final project report been made cohesively

Badewi, A. (2016). The impact of project management (PM) and benefits management (BM) practices on project success: Towards developing a project benefits governance framework. International Journal of Project Management, 34(4), 761-778.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Fleming, Q. W., & Koppelman, J. M. (2016, December). Earned value project management. Project Management Institute.

Fuller, M. A., Valacich, J. S., George, J. F., & Schneider, C. (2017). Information Systems Project Management: A Process and Team Approach, Edition 1.1. Prospect Press.

Greene, J., & Stellman, A. (2018). Head First PMP: A Learner’s Companion to Passing the Project Management Professional Exam. O’Reilly Media.

Harris, E. (2017). Strategic project risk appraisal and management. Routledge.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heagney, J. (2016). Fundamentals of project management. Amacom.

Kermanshachi, S., Dao, B., Shane, J., & Anderson, S. (2016). An empirical study into identifying project complexity management strategies. Procedia Engineering, 145, 603-610.

Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Liu, S. (2016). How the user liaison’s understanding of development processes moderates the effects of user-related and project management risks on IT project performance. Information & Management, 53(1), 122-134.

Lock, D. (2017). The essentials of project management. Routledge.

Martens, M. L., & Carvalho, M. M. (2017). Key factors of sustainability in project management context: A survey exploring the project managers’ perspective. International Journal of Project Management, 35(6), 1084-1102.

Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for the practicing project manager. John Wiley & Sons.

Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and technology. Routledge.