Project Management For Web Application Development

Indented WBS

Project Management concept has been largely developed for evaluating the development of project and forming the appropriate development of project tools and options. The development of project operations is being utilized for realizing the use of project management tools and options. The development of web applications had been possible with the help of project tools and options. The deployment of web based application and its concepts would be helpful for forming the analysis of the project tools and options. The social media research centre had realized the importance of technology for the project operations. The development of project would be eased by the use of project management tools and principles.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

WBS

Task Name

0

Development of Web Application for Social Media Research Centre

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

1

   Initialization and Planning for the project

1.1

      Analysis of project objectives

1.2

      Developing project operation list

1.3

      Estimating Project Budget

1.4

      Making Project Schedule

1.5

      Charter development

1.6

      Charter is signed

1.7

      Project Management Methodology is selected

1.8

      Plan outline is developed

1.9

      Complete Plan is developed

1.10

      Plan is approved

2

   Designing of Application

2.1

      Design requirements is evaluated

2.2

      Designing platform, tools, and method is selected

2.3

      Outline of design is developed

2.4

      Design is completed

3

   Database is developed

3.1

      Database requirements is analyzed

3.2

      Database is integrated with the design

3.3

      Selection of Storage drive

3.4

      Database is created

3.5

      Database is reviewed

4

   Application Development

4.1

      Application platform is analyzed

4.2

      Development tools is evaluated

4.3

      Programming is done

4.4

      Coding is done for implementing security option

4.5

      Application is developed

4.6

      Application is reviewed

5

   Testing Phase

5.1

      UX testing

5.2

      Typography testing

5.3

      Errors are evaluated

6

   Final Documentation and Training

6.1

      Results of testing is developed in report

6.2

      Project Closure and progress documents are created

6.3

      Training Manuals are developed

6.4

      Training is being given

7

   Closure

Figure 1: Gantt chart of the project

WBS

Task Name

Duration

Start

Finish

Predecessors

Resource Names

Cost

0

Development of Web Application for Social Media Research Centre

124 days

Mon 4/3/17

Thu 9/21/17

$49,840.00

1

   Initialization and Planning for the project

24 days

Mon 4/3/17

Thu 5/4/17

$10,200.00

1.1

      Analysis of project objectives

3 days

Mon 4/3/17

Wed 4/5/17

Systems Analyst

$1,680.00

1.2

      Developing project operation list

2 days

Thu 4/6/17

Fri 4/7/17

2

Program Team member_1

$800.00

1.3

      Estimating Project Budget

3 days

Mon 4/10/17

Wed 4/12/17

3

Program Team member_2

$1,200.00

1.4

      Making Project Schedule

2 days

Thu 4/13/17

Fri 4/14/17

4

Program Team member_2

$800.00

1.5

      Charter development

3 days

Mon 4/17/17

Wed 4/19/17

5

Program Team member_1

$1,200.00

1.6

      Charter is signed

1 day

Thu 4/20/17

Thu 4/20/17

6

Project Manager

$640.00

1.7

      Project Management Methodology is selected

2 days

Fri 4/21/17

Mon 4/24/17

7

Project Manager

$1,280.00

1.8

      Plan outline is developed

2 days

Tue 4/25/17

Wed 4/26/17

8

Team Member_1

$560.00

1.9

      Complete Plan is developed

5 days

Thu 4/27/17

Wed 5/3/17

9

Team Member_2

$1,400.00

1.10

      Plan is approved

1 day

Thu 5/4/17

Thu 5/4/17

10

Project Manager

$640.00

2

   Designing of Application

13 days

Fri 5/5/17

Tue 5/23/17

$5,200.00

2.1

      Design requirements is evaluated

3 days

Fri 5/5/17

Tue 5/9/17

11

Graphic Designer

$1,200.00

2.2

      Designing platform, tools, and method is selected

4 days

Wed 5/10/17

Mon 5/15/17

13

Graphic Designer

$1,600.00

2.3

      Outline of design is developed

2 days

Tue 5/16/17

Wed 5/17/17

14

Graphic Designer

$800.00

2.4

      Design is completed

4 days

Thu 5/18/17

Tue 5/23/17

15

Graphic Designer

$1,600.00

3

   Database is developed

15 days

Wed 5/24/17

Tue 6/13/17

$6,320.00

3.1

      Database requirements is analyzed

2 days

Wed 5/24/17

Thu 5/25/17

16

Database Administrator

$800.00

3.2

      Database is integrated with the design

3 days

Fri 5/26/17

Tue 5/30/17

18

Database Administrator

$1,200.00

3.3

      Selection of Storage drive

2 days

Wed 5/31/17

Thu 6/1/17

19

Database Administrator

$800.00

3.4

      Database is created

6 days

Fri 6/2/17

Fri 6/9/17

20

Database Administrator

$2,400.00

3.5

      Database is reviewed

2 days

Mon 6/12/17

Tue 6/13/17

21

Systems Analyst

$1,120.00

4

   Application Development

28 days

Wed 6/14/17

Fri 7/21/17

$11,520.00

4.1

      Application platform is analyzed

2 days

Wed 6/14/17

Thu 6/15/17

22

Application Programmer

$800.00

4.2

      Development tools is evaluated

3 days

Fri 6/16/17

Tue 6/20/17

24

Application Programmer

$1,200.00

4.3

      Programming is done

7 days

Wed 6/21/17

Thu 6/29/17

25

Application Programmer

$2,800.00

4.4

      Coding is done for implementing security option

7 days

Fri 6/30/17

Mon 7/10/17

26

Application Programmer

$2,800.00

4.5

      Application is developed

7 days

Tue 7/11/17

Wed 7/19/17

27

Application Programmer

$2,800.00

4.6

      Application is reviewed

2 days

Thu 7/20/17

Fri 7/21/17

28

Systems Analyst

$1,120.00

5

   Testing Phase

9 days

Mon 7/24/17

Thu 8/3/17

$4,320.00

5.1

      UX testing

3 days

Mon 7/24/17

Wed 7/26/17

29

Quality Assurance Tester

$1,440.00

5.2

      Typography testing

3 days

Thu 7/27/17

Mon 7/31/17

31

Quality Assurance Tester

$1,440.00

5.3

      Errors are evaluated

3 days

Tue 8/1/17

Thu 8/3/17

32

Quality Assurance Tester

$1,440.00

6

   Final Documentation and Training

34 days

Fri 8/4/17

Wed 9/20/17

$12,280.00

6.1

      Results of testing is developed in report

6 days

Fri 8/4/17

Fri 8/11/17

33

Team Member_1

$1,680.00

6.2

      Project Closure and progress documents are created

8 days

Mon 8/14/17

Wed 8/23/17

35

Program Team member_2

$3,200.00

6.3

      Training Manuals are developed

5 days

Thu 8/24/17

Wed 8/30/17

36

Team Member_2

$1,400.00

6.4

      Training is being given

15 days

Thu 8/31/17

Wed 9/20/17

37

Program Team member_1

$6,000.00

7

   Closure

1 day

Thu 9/21/17

Thu 9/21/17

38

$0.00

The timed resource usages is being given below,

Resource Name

Work

Cost

Application Programmer

208 hrs

$10,400.00

   Application platform is analyzed

16 hrs

$800.00

   Development tools is evaluated

24 hrs

$1,200.00

   Programming is done

56 hrs

$2,800.00

   Coding is done for implementing security option

56 hrs

$2,800.00

   Application is developed

56 hrs

$2,800.00

Database Administrator

104 hrs

$5,200.00

   Database requirements is analyzed

16 hrs

$800.00

   Database is integrated with the design

24 hrs

$1,200.00

   Selection of Storage drive

16 hrs

$800.00

   Database is created

48 hrs

$2,400.00

Graphic Designer

104 hrs

$5,200.00

   Design requirements is evaluated

24 hrs

$1,200.00

   Designing platform, tools, and method is selected

32 hrs

$1,600.00

   Outline of design is developed

16 hrs

$800.00

   Design is completed

32 hrs

$1,600.00

Program Team member_1

160 hrs

$8,000.00

   Developing project operation list

16 hrs

$800.00

   Charter development

24 hrs

$1,200.00

   Training is being given

120 hrs

$6,000.00

Program Team member_2

104 hrs

$5,200.00

   Estimating Project Budget

24 hrs

$1,200.00

   Making Project Schedule

16 hrs

$800.00

   Project Closure and progress documents are created

64 hrs

$3,200.00

Quality Assurance Tester

72 hrs

$4,320.00

   UX testing

24 hrs

$1,440.00

   Typography testing

24 hrs

$1,440.00

   Errors are evaluated

24 hrs

$1,440.00

Project Manager

32 hrs

$2,560.00

   Charter is signed

8 hrs

$640.00

   Project Management Methodology is selected

16 hrs

$1,280.00

   Plan is approved

8 hrs

$640.00

Systems Analyst

56 hrs

$3,920.00

   Analysis of project objectives

24 hrs

$1,680.00

   Database is reviewed

16 hrs

$1,120.00

   Application is reviewed

16 hrs

$1,120.00

Team Member_1

64 hrs

$2,240.00

   Plan outline is developed

16 hrs

$560.00

   Results of testing is developed in report

48 hrs

$1,680.00

Team Member_2

80 hrs

$2,800.00

   Complete Plan is developed

40 hrs

$1,400.00

   Training Manuals are developed

40 hrs

$1,400.00

 The diagrammatic representation of time phased budget is being given below, 

Figure 2: Time Phase Budget of the project

Labor Cost

 $38,820.00

Fringe (@20%)

 $8,020.00

Cost of hardware

 $3,000.00

Total budget

 $49,840.00

 Assumptions and Constraints

The project had been developed for developing the appropriate development of web application for Social Media Research Centre. The details of assumptions and constraints are given in table below,

Assumptions: The development of project activities had been formed for forming the appropriate web application implementation for the Social Media Research Centre. The project had been assumed to complete in less than 8 months of durations. The total number of days for the project is 124 days. The workers had to form smart development of operations and functions. The fringe value had been considered for 20%.

Constraints: The constraints of the project are the schedules, and resource allocation. The allocation of resource is a major source for the development of the project activities. The limitation of project budget to be less than AUD 50,000 would also serve the purpose of project operations. The project is also scheduled to complete in 8 months of duration.

 Budge Estimation: The estimation of budget is being developed by using resource allocation in the project. The development of project operations is being formed for forming support to the development of project operations. There are some development models that would help in easing the functions of development of operations. The direct costs would be evaluated in the project of estimation of budget. The simple and easy to use project would form the accommodate development of project in the organization. The direct costs like salaries of team members, costs of materials, and other costs would serve the known knowns of the project. The unknowns in the project include financial related risk management activities. These unknown factors would help in developing system modulation project.

The risk register is being shown below,

Privacy Infiltration

Design Errors

Resource Issue

Early completion

Ref no

REF_0065

(Negative)

REF_0066

(Negative)

REF_0067

(Negative)

REF_0068

(Positive)

Rank

1st

2nd

3rd

4th

Owner

Security expert

Designer

Budgeter

Project Manager

Likelihood

Possible

Likely

Likely

Rare

Impact

Severe

High

Moderate

Minor

Status

Active

Active

Active

Active

Mitigation

Encryptions should be used

Designing method should be selected

Contingency budget allocations should be used

Using early completion for reviewing the application developed

The quality management plan can be developed by following the objectives of the project and developing assurance statement. The objectives to follow project are,

  1. Ensuring the project operations are customer eccentric focusing on the needs of project
  2. Application developed is effective and study compliance
  3. Customer’s satisfaction would be achieved

The 3 quality issues of project are,

Security: It is the most primary object that faces the issues of development of operations at social media research centre

Performance: The functions of system would be incompatible with the development of operations

Quality: The assurance of quality is being done for forming the smart development of project quality issues.

Project Name: Development of Web Application for Social Media Research Centre

Completion period: 8 Months

Project Manager: [Enter Your name]

Project budget:  AUD 49940.00

Activities

Due Date

Person responsible

 

The storage at Social Media Center would be developed

Database Administrator

Development of project plan for project activities

Planner

Charter creations for the project

Project Manger

Risk register is developed

Quality team

Training is developed

Team member

Supporting the plan and forming employees operations

Team Member

Final Project Report is made

Program manger

Develop Documents for Lesson Learned Documents

Team member

Develop Training Documents

Sales Expert

Handover of team reports for signing

Program manager

sign off team members

Team members

Signed By:

<<name of student>>

Stakeholder

Conclusion

The advancement of venture operations is being used for understanding the utilization of venture administration apparatuses and alternatives. The advancement of web applications had been conceivable with the assistance of venture apparatuses and choices. The arrangement of electronic application and its ideas would be useful for shaping the investigation of the venture instruments and alternatives. The online networking research focus had understood the significance of innovation for the venture operations.

Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.

Heagney, J. (2016). Fundamentals of project management. AMACOM Div American Mgmt Assn.

Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Leach, L. P. (2014). Critical chain project management. Artech House.

Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success. International Journal of Project Management, 32(2), 202-217.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Turner, J. R. (2014). The handbook of project-based management (Vol. 92). New York, NY: McGraw-hill.

Walker, A. (2015). Project management in construction. John Wiley & Sons.