Redesign Of 5th Floor At OPAIC: A Project Management Plan

Project Management Approach

OPAIC is a New Zealand based polytechnic educational organization that has a multistoried campus building. The institution is looking to redesign the 5th floor in order to suit the requirements of the new curriculum. Accordingly, the board has hired a project management team for handling and management of the project. The board has also asked to put forward a project management plan that will be used for the project if it gets approved by the board.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

This report is based on the development of the project management plan for the redesign of the 5th floor of OPAIC as per the requirements set by the management board.

Any project requires a specific management approach in order to fulfill its requirements and complete all the deliverables that are specified in the requirements. There are many types of project management approaches that are mainly chosen based on the nature and requirements of the project (Burke & Barron, 2014). For example, software projects have specific types of approaches while construction projects require different approaches.

For this particular project, the most suitable project management approach will be “Waterfall Model”, also known as traditional project management approach. In this project management approach, specific milestones must be defined and placed between each task and the project approach must ensure the milestones are reached at the right schedules and in the right chronologic order (Conforto et al., 2014). Based on the process of this approach, a timeline can be developed using an appropriate work breakdown structure that will contain all the work packages as well as the pre-defined milestones.

Before proceeding further with the project management plan, the scope of the project needs to be defined (Kerzner & Kerzner, 2017). The project scope will define the boundary within which, the project must remain and fulfill all the deliverables that will be set as per the requirements of the project.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The main scope of the project is the delivery of the newly designed 5th floor of the OPAIC building. Other in scope items are specified as follows.

  • Survey of the existing 5thfloor of the building is within the scope of the project
  • Studying the requirements of the proposed design is within the scope of the project
  • Appointment of human resources for the project is within the scope of the project
  • Restructuring of the 5thfloor is within the scope of the project
  • Addition of different walls in the 5thfloor is within the scope of the project

In order to manage the project within feasibility limits, it is required to define an appropriate schedule and budget within which the project must be completed (Crawford, 2014). Moreover, suitable and sufficient skilled labor has to be appointed who will work on the development of new 5th floor design as per the specifications.

The schedule baseline chart for the project is shown as follows.

Task Name

Duration

Start

Finish

Floor Redesign for OPAIC

165 days

Mon 2/4/19

Fri 9/20/19

   Initial Discussion and Planning

12 days

Mon 2/4/19

Tue 2/19/19

      Project Management Team Meeting

12 days

Mon 2/4/19

Tue 2/19/19

         Discuss the Redesign Requirements

3 days

Mon 2/4/19

Wed 2/6/19

         Develop a Proposal for the Project

3 days

Thu 2/7/19

Mon 2/11/19

         Submit Proposal to Management

2 days

Tue 2/12/19

Wed 2/13/19

         Propose an Estimated Overall Budget Required for the Project

2 days

Thu 2/14/19

Fri 2/15/19

         Determine Feasibility of the Project

2 days

Mon 2/18/19

Tue 2/19/19

      Receive Board Approval Regarding the Project

0 days

Tue 2/19/19

Tue 2/19/19

   Project Planning Phase

24 days

Wed 2/20/19

Mon 3/25/19

      Create Team for Project Management

2 days

Wed 2/20/19

Thu 2/21/19

      Create an Idea Regarding Project Roadmap

2 days

Fri 2/22/19

Mon 2/25/19

      Prepare Project Charter

6 days

Tue 2/26/19

Tue 3/5/19

         Develop Project Scope

1 day

Tue 2/26/19

Tue 2/26/19

         Determine Schedule Baseline for Project

1 day

Wed 2/27/19

Wed 2/27/19

         Determine Budget Necessary for the Project

2 days

Thu 2/28/19

Fri 3/1/19

         Determine Project Feasibility

2 days

Mon 3/4/19

Tue 3/5/19

      Release Tender Regarding Project Contractor

3 days

Wed 3/6/19

Fri 3/8/19

      Select Contractor for the Project

2 days

Mon 3/11/19

Tue 3/12/19

      Discuss the Requirements of the Project

5 days

Wed 3/13/19

Tue 3/19/19

      Discuss about the Human Resources Required for the Project

1 day

Wed 3/20/19

Wed 3/20/19

      Discuss Timeframe, Budget and Design of the Floor

3 days

Thu 3/21/19

Mon 3/25/19

      Proceed with the Project

0 days

Mon 3/25/19

Mon 3/25/19

   Project Initiation

20 days

Tue 3/26/19

Mon 4/22/19

      Receive Permit for Floor Work

5 days

Tue 3/26/19

Mon 4/1/19

      Receive Approval from Board for Working on the Floor

2 days

Tue 4/2/19

Wed 4/3/19

      Develop Floor Blueprint

5 days

Thu 4/4/19

Wed 4/10/19

      Review the Floor Design

2 days

Thu 4/11/19

Fri 4/12/19

      Recruit Human Resources (Work Force)

2 days

Mon 4/15/19

Tue 4/16/19

      Procure Construction Materials

2 days

Wed 4/17/19

Thu 4/18/19

      Procure Floor Design Equipments

2 days

Fri 4/19/19

Mon 4/22/19

      Proceed to Project Initiation

0 days

Mon 4/22/19

Mon 4/22/19

   Project Execution

99 days

Tue 4/23/19

Fri 9/6/19

      Survey the Existing Floor Condition

4 days

Tue 4/23/19

Fri 4/26/19

      Remove Unwanted Materials and Walls from the Floor

2 days

Mon 4/29/19

Tue 4/30/19

      Place Design Parameters on the Floor

2 days

Wed 5/1/19

Thu 5/2/19

      Prepare Room Frameworks

15 days

Fri 5/3/19

Thu 5/23/19

      Install Structural Materials

15 days

Fri 5/24/19

Thu 6/13/19

      Divide Rooms as per the Requirements

5 days

Fri 6/14/19

Thu 6/20/19

      Create Structural Separations between the Zones

10 days

Fri 6/21/19

Thu 7/4/19

      Install Electrical Wirings

5 days

Fri 7/5/19

Thu 7/11/19

      Install Academic Equipments as Required

2 days

Fri 7/12/19

Mon 7/15/19

      Place Accessory Materials and Structures

2 days

Tue 7/16/19

Wed 7/17/19

      Install Computers and Other Accessory Equipments

5 days

Thu 7/18/19

Wed 7/24/19

      Finishing Electrical and Other Works

10 days

Thu 7/25/19

Wed 8/7/19

      Additional Works

20 days

Thu 8/8/19

Wed 9/4/19

         Add Colours to Floor Rooms

5 days

Thu 8/8/19

Wed 8/14/19

         Add Colours to Room Exteriors

5 days

Thu 8/15/19

Wed 8/21/19

         Testing of the Electrical Connections

5 days

Thu 8/22/19

Wed 8/28/19

         Testing of the Safety Equipments

2 days

Thu 8/29/19

Fri 8/30/19

         Testing of the Academic Equipments

3 days

Mon 9/2/19

Wed 9/4/19

      Completion of Floor Redesign

2 days

Thu 9/5/19

Fri 9/6/19

      Handover the Project

0 days

Fri 9/6/19

Fri 9/6/19

   Project Closure

10 days

Mon 9/9/19

Fri 9/20/19

      Review of the Project

5 days

Mon 9/9/19

Fri 9/13/19

      Project Appraisal

3 days

Mon 9/16/19

Wed 9/18/19

      Pay All Wages

1 day

Thu 9/19/19

Thu 9/19/19

      Stakeholder Sign Off

1 day

Fri 9/20/19

Fri 9/20/19

      Project Closed

0 days

Fri 9/20/19

Fri 9/20/19

Project Scope and Management Plan

The key resources of the project are shown in the following table.

Resource Name

Type

Max. Units

Std. Rate

Ovt. Rate

Project Manager

Work

100%

$200.00/hr

$0.00/hr

Construction Manager

Work

100%

$120.00/hr

$0.00/hr

Project Supervisor

Work

100%

$125.00/hr

$0.00/hr

Finance Manager

Work

100%

$135.00/hr

$0.00/hr

Workers

Work

100%

$500.00/hr

$0.00/hr

Construction Materials and Other Costs

Material

$20,000.00

The milestones of the project are as follows.

  • Submission of Project Proposal
  • Development of Project Charter for the Project
  • Approval to Proceed with Project Work
  • Project Handover
  • Stakeholder Sign Off

Any project requires certain changes during the execution phase that is mainly dependant on the complexity and nature of the project. Moreover, the changes will depend on how the project is progressing and how any new changes will be able to enhance the quality of the project (Aga, Noorderhaven & Vallejo, 2016). For introducing change management in a project, it is also important to monitor the progress of the project and also implement the changes at the right time so that they have the maximum positive impact of the project.

In this project, change management may be required regarding the design of the 5th floor. Monitoring the progress of the project, at one point of time, the management may decide that certain changes are required that will further enhance the quality of the project. In this case, it is to be determined whether these changes will be absolutely necessary and also feasible for the project in terms of cost, time for implementation and others (Harrison & Lock, 2017). Furthermore, before implementation, the project manager must call a team meeting to discuss the proposed changes and determine whether the team is willing to work on the changes. After everything is finalized, the changes can be finally implemented in the project by the project manager.

In order to successfully execute a project, proper communication is required between the stakeholders and other human resources involved it in. The communication process also ensures there is a constant flow of information between the stakeholders regarding the progress of the project (Marchewka, 2014). The flow of information should also be in an appropriate format and should be processed at the right time. For this particular project, the communication management plan is shown in the following table.

Stakeholder

Communication Purpose

Communication Frequency

Communication Medium

Project Manager

Any update on project, risk or challenge encountered, change requirement, expenditure report, progress update and others

Daily (recommended) / Weekly (usual)

Face to face meeting or written reports (paper or electronic documents)

Design Engineer

Design and project requirements

During project planning / as required

Face to face meeting / requirement document

Construction Manager

Construction related work requirements in the floor

Daily

Face to face communication / design document

Project Supervisor

Reporting requirements

Weekly

Face to face meeting

Finance Manager

Finance related problems and requirements

As required

Finance reports

The cost baseline of the project is shown in the following chart (Heldman, 2018).

Task Name

Resource Names

Cost

Floor Redesign for OPAIC

$554,240.00

   Initial Discussion and Planning

$55,680.00

      Project Management Team Meeting

$55,680.00

         Discuss the Redesign Requirements

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$13,920.00

         Develop a Proposal for the Project

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$13,920.00

         Submit Proposal to Management

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$9,280.00

         Propose an Estimated Overall Budget Required for the Project

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$9,280.00

         Determine Feasibility of the Project

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$9,280.00

      Receive Board Approval Regarding the Project

Project Manager

$0.00

   Project Planning Phase

$44,320.00

      Create Team for Project Management

Project Manager

$3,200.00

      Create an Idea Regarding Project Roadmap

Construction Manager

$1,920.00

      Prepare Project Charter

$11,760.00

         Develop Project Scope

Construction Manager, Project Supervisor

$1,960.00

         Determine Schedule Baseline for Project

Construction Manager, Project Supervisor

$1,960.00

         Determine Budget Necessary for the Project

Construction Manager, Project Supervisor

$3,920.00

         Determine Project Feasibility

Construction Manager, Project Supervisor

$3,920.00

      Release Tender Regarding Project Contractor

Construction Manager, Project Supervisor

$5,880.00

      Select Contractor for the Project

Construction Manager, Project Supervisor

$3,920.00

      Discuss the Requirements of the Project

Construction Manager, Project Supervisor

$9,800.00

      Discuss about the Human Resources Required for the Project

Construction Manager, Project Supervisor

$1,960.00

      Discuss Timeframe, Budget and Design of the Floor

Construction Manager, Project Supervisor

$5,880.00

      Proceed with the Project

Construction Manager, Project Supervisor

$0.00

   Project Initiation

$39,200.00

      Receive Permit for Floor Work

Construction Manager

$4,800.00

      Receive Approval from Board for Working on the Floor

Construction Manager

$1,920.00

      Develop Floor Blueprint

Construction Manager

$4,800.00

      Review the Floor Design

Construction Manager

$1,920.00

      Recruit Human Resources (Work Force)

Construction Manager

$1,920.00

      Procure Construction Materials

Construction Manager, Construction Materials and Other Costs[1]

$21,920.00

      Procure Floor Design Equipments

Construction Manager

$1,920.00

      Proceed to Project Initiation

Construction Manager, Project Supervisor

$0.00

   Project Execution

$396,000.00

      Survey the Existing Floor Condition

Workers

$16,000.00

      Remove Unwanted Materials and Walls from the Floor

Workers

$8,000.00

      Place Design Parameters on the Floor

Workers

$8,000.00

      Prepare Room Frameworks

Workers

$60,000.00

      Install Structural Materials

Workers

$60,000.00

      Divide Rooms as per the Requirements

Workers

$20,000.00

      Create Structural Separations between the Zones

Workers

$40,000.00

      Install Electrical Wirings

Workers

$20,000.00

      Install Academic Equipments as Required

Workers

$8,000.00

      Place Accessory Materials and Structures

Workers

$8,000.00

      Install Computers and Other Accessory Equipments

Workers

$20,000.00

      Finishing Electrical and Other Works

Workers

$40,000.00

      Additional Works

$80,000.00

         Add Colours to Floor Rooms

Workers

$20,000.00

         Add Colours to Room Exteriors

Workers

$20,000.00

         Testing of the Electrical Connections

Workers

$20,000.00

         Testing of the Safety Equipments

Workers

$8,000.00

         Testing of the Academic Equipments

Workers

$12,000.00

      Completion of Floor Redesign

Workers

$8,000.00

      Handover the Project

Workers

$0.00

   Project Closure

$19,040.00

      Review of the Project

Project Manager

$8,000.00

      Project Appraisal

Project Manager

$4,800.00

      Pay All Wages

Project Manager

$1,600.00

      Stakeholder Sign Off

Construction Manager, Finance Manager, Project Manager, Project Supervisor

$4,640.00

      Project Closed

Project Manager

$0.00

It is very much important to develop a suitable cost management plan in order to ensure the project costs do not exceed the total overall budget. Hence, the finance manager is assigned to monitor the project expenses and ensure no extra costs are occurring during the project (Ramazani & Jergeas, 2015). The project team is required to submit project finance report at the end of each week to the project finance manager that he will review and report to the management.

Schedule Baseline and Work Breakdown Structure with Key Resources

For the purpose of the project, procurement of suitable materials is necessary. In addition to the materials, it is also needed to be ensured that the quality of the materials is good enough to be used in the project (Walker, 2015). Furthermore, the overall quality of the project also needs to meet the specific design and construction standards and for that purpose, the materials used must be of the best quality but also at reasonable costs in order to avoid too much extra expenses in the project.

For the procurement of the materials, a procurement manager needs to be appointed who is not only experienced in marketing but also is able to identify the quality of materials bought from the vendors. During procurement, the following points should be considered.

Seller Background – Before purchasing materials from the seller, the procurement manager must analyze and check the background of the seller to determine whether he is reliable or not. Any seller with poor track record and background must be rejected.

Material Quality – The procurement manager must check the quality of the materials before purchasing them (Tyssen, Wald & Spieth, 2014). He can check the materials against certain quality standards and if they do not fulfill the standards, they can be rejected from purchasing.

Material Price – During the purchase process, the procurement manager must remember the project budget and ensure the purchased materials are not too costly and does not cross the allocated budget for the procurement.

The procurement can be done through the PO (Purchase Order) model in which, after all the verifications, the procurement manager will place a purchase order to the seller who will then deliver the materials and take payments for the same.

In addition to the material quality, it is also required to maintain a suitable quality of the project such that it meets the design and quality standards set during the planning of the project. Furthermore, before starting with the project, a Quality Control (QC) department needs to be set up who will be responsible for controlling the quality of the project outcome (Trendowicz & Jeffery, 2014). This department / team will monitor the progress of the project and conduct certain quality tests from time to time to ensure the quality standards are met. The team will also need to create weekly reports regarding the project progress and submit them to the management for further evaluation.

Another duty of the QC team is to monitor the work processes that are being executed every day during the course of the project. They need to determine whether the project is executed as per the predetermined schedule and the budget breakdown as defined earlier (Schwalbe, 2015). In case the project is lagging behind the created schedule, the QC team should escalate about the same to the management so that suitable change management actions can be taken to prevent any delay to the project.

There are several risks associated with the project that are listed as follows along with the management plan for each of the risks (Niazi et al., 2016).

Risk Description

Chance of Occurrence

Impact on Project

Mitigation Plan

Due to the construction work on the 5th floor, the other floors may get affected.

Very High

Very High

During the construction and redesign work, special care should be taken such that the other floors are not affected during the works.

The design may not meet suitable standards and hence, it may not be approved by the board or even the local council.

Medium

Very High

During the planning phase, the design should be finalized and verified; license should be taken from the council to go ahead with the project.

The project expenses may result in budget overshoot due to uncontrolled expenditure during project work or occurrence of unforeseen accidents

Medium

High

The quality control team should monitor project work and ensure the budget is spent as per the planning. There can be some additional budget that is kept for contingency situations.

Before the project is handed over and rolled out, the following approvals are needed.

Approval From

Approval For

Signature of Approver

Management Board

Proceed with Project

________________________

Local Council

Construction Work at 5th Floor

________________________

Management Board

Start Execution of the Project

________________________

All Stakeholders

Final Handover

________________________

Conclusion

This report is used to develop a suitable project plan and define all the necessary parameters of the project. The main objective of this project is to redesign the 5th floor of OPAIC and the management has asked to form a project management team who will take care of the project. The overall quality of the project needs to meet the specific design and construction standards and for that purpose, the materials used must be of the best quality but also at reasonable costs in order to avoid too much extra expenses in the project. As per the initial estimations regarding the project, a total time of 165 working days are required along with an overall budget of $554,240.

Aga, D. A., Noorderhaven, N., & Vallejo, B. (2016). Transformational leadership and project success: The mediating role of team-building. International Journal of Project Management, 34(5), 806-818.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Burke, R., & Barron, S. (2014). Project management leadership: building creative teams. John Wiley & Sons.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Crawford, J. K. (2014). Project management maturity model. Auerbach Publications.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kilibarda, G. D., Šobaji?, V. M., Beri?, I. M., & Jovanovi?, P. M. (2016). Software project management. Tehnika, 71(1), 145-152.

Kundra, T., & Sharma, A. (2015). Software project management. Int. J. Res.

Lee, M. R. (2016). Leading virtual project teams: Adapting leadership theories and communications techniques to 21st century organizations. Auerbach Publications.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Niazi, M., Mahmood, S., Alshayeb, M., Qureshi, A. M., Faisal, K., & Cerpa, N. (2016). Toward successful project management in global software development. International Journal of Project Management, 34(8), 1553-1567.

Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great: The benefits of investment in project management training and education. International Journal of Project Management, 33(1), 41-52.

Redick, A., Reyna, I., Schaffer, C., & Toomey, D. (2014). Four-factor model for effective project leadership competency. Journal of Information Technology and Economic Development, 5(1), 53.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Silva, P., Moreno, A. M., & Peters, L. (2015). Software Project Management: Learning from Our Mistakes. IEEE Software, (3), 40-43.

Trendowicz, A., & Jeffery, R. (2014). Software project effort estimation. Foundations and Best Practice Guidelines for Success, Constructive Cost Model–COCOMO pags, 277-293.

Tyssen, A. K., Wald, A., & Spieth, P. (2014). The challenge of transactional and transformational leadership in projects. International Journal of Project Management, 32(3), 365-375.

Walker, A. (2015). Project management in construction. John Wiley & Sons.