Teaching And Learning System (TLS) Project Report

Functional and Non-functional Requirements of TLS

The High Quality Institute (HQI), a technological training institute operates in the educational sector, offering courses in information and communication technology. The institution seeks to develop and deploy an advance Teaching and Learning System (TLS). The intended system will provide a range of services such as staff and student emails and a database management system for the institution. As such the project to develop this application will also entail configuring a database server a management, web and email servers.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Besides the configuration of the servers, a complete IT infrastructure has to be established at the institutions to support the deployment of the intended system as well as provide a secure and highly available communication and networking platform. The intended network will use a range of network devices including routers, intrusion detection systems and backup solutions.

The intension of the management at the institution is to develop and deploy two online systems; an Undergraduate Learning System (ULS) and a Postgraduate Learning System (PLS). These systems will be developed internally by the IT department of the institute.

The aim and objective of this report is to present a system analysis and design of the intended system for the institution. This will entail identifying the functional and non-functional requirements of the proposed Teaching and Learning System (TLS). The report will present a Work Breakdown Structure which will identify the various tasks required to accomplish this project. A PERT/CPM chart will then be developed. This will be followed by the identification of the critical path and time requirements for the project. The report also presents a data model of the student registration process by use of class diagrams. Finally the report presents calculations for the net present value, payback period and return on investment.

Theoretically, functional requirements refer to the expected functioning of the system to be developed (Wiegers & Beatty, 2013). These are the system’s features or what the system should do or provider for users. Functional requirements include the functions, reports, online queries and details of data to be held by the system (Wiegers & Beatty, 2013). On the other hand, Non-functional requirements refer to controls, constraints and attributes, which describe the systems and can be used in judging the performance of the system. These include attributes such as security, performance level, availability, reliability and usability (Wiegers & Beatty, 2013).  

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

The functional requirements for TLS are;

  • Enable assigning a student to an advisor
  • Enable units registration
  • Maintain student details and
  • Maintain details of assigned advisor
  • Maintain Course and Units details

Although the case study does not explicitly mention the course and units, from the other functional requirements, the system must have a function to keep track of all courses and units offered by the institution.

  • Usability: the developed system has to be easy to use, to facilitate use by novice computer users.
  • Availability: the system should be highly available at any time. The underlying infrastructure has to be designed in a way that provides high availability; with minimal or no downtime at all
  • Reliability: the system should perform the required tasks consistently and reliably.
  • Security: the system will hold personally identifiableinformation; as such the system should provide adequate data security for data in databases and on transit over the internet (Burke, 2013).

Work Breakdown Structure of TLS Project

A Work breakdown structure WBS outlines activities necessary to be performed in a project to attain the project’s deliverables. A WBS outlines the activities in a hierarchical subdivision of the project’s tasks into work areas, with the lowest level forming a work package (Dennis,Wixom & Tegarden, 2015). In a project a WBS forms the base of all the project management tasks from project planning, cost estimation, resource allocation and project scheduling. The Project Management Body of Knowledge (PMBOK) defines a work breakdown structure as a “deliverable oriented hierarchical decomposition of the work to be executed by the project team” (Burke, 2013).  A WBS provides a structural view into a project. The main functions of a work breakdown structure include;

  • Enables scope definition
  • Facilitates resource allocation to tasks
  • Enables the establishment of a control baseline
  • Provides means of measuring project progress and accomplishments by defining milestones (Burke, 2013)

The work breakdown Structure for this project is as follows;

Task No

Description

Predecessors

Duration

1. 

Teaching and Learning System

180 days

2. 

   Project Initiation and Planning

7 days

3. 

      Project kickoff meeting

1 day

4. 

      Stakeholder Identification

1 day

5. 

      Risk Identification

4

2 days

6. 

      Development of a project plan

5

3 days

7. 

   Milestone 1: Project Charter Approved

0 days

8. 

   Requirement Analysis

12 days

9. 

      Requirement gathering

5 days

10. 

      Functional Requirements analysis

9

4 days

11. 

      Analysis of non-functional requirements

10

3 days

12. 

   Milestone 2: System Requirements approved

0 days

13. 

   Application Design

12 days

14. 

      Application Basic Design

5 days

15. 

      Technical Feasibility Assessment

14

2 days

16. 

      Architectural Reference Group Presentation

14,15

2 days

17. 

      Application Detailed Design

15

5 days

18. 

   Milestone 3: Detailed Design Approval

0 days

19. 

   Infrastructure Development

11

11 days

20. 

      Network design

12

3 days

21. 

      Laying of the network

20

3 days

22. 

      Servers installation

21

2 days

23. 

      Network and Servers configuration

22

2 days

24. 

      Network testing

23

1 day

25. 

   Development

44 days

26. 

      Coding

18

20 days

27. 

      Unit testing

26

2 days

28. 

      Integration testing

26

2 days

29. 

      Debugging

28

2 days

30. 

   Milestone 4: Development Complete

0 days

31. 

   Testing

16 days

32. 

      Complete System testing

30

2 days

33. 

      Debugging

32

2 days

34. 

      User Acceptance Testing

32

2 days

35. 

      System & User Interface Bug Fix

33,34

2 days

36. 

   Milestone 5: Testing Completed

0 days

37. 

   Launch

6 days

38. 

      User Training

36

5 days

39. 

      Deployment and GoLive

38

1 day

40. 

   Closure

10 days

41. 

      Document Lessons Learnt

39

1 day

42. 

      Release Project Team

41

1 day

43. 

      Finalize and Archive Project Documentation

41

3 days

44. 

      Close Project

43

1 day

The critical path for the completion of the project is made up of;

  • Project Initiation and scheduling
  • Requirement analysis
  • Application design
  • Programming
  • Hardware /network configurations
  • Unit Testing
  • System testing
  • User training
  • Project closure 

In calculating the NPV the rate was taken to be 0 since the investment is a system

YEAR

No

Category

0

1

2

3

4

5

1

Value of benefits

7000

7000

7000

7000

7000

2

Development Cost

-20000

0

0

0

0

0

3

Annual Expenses

-2000

-2000

-2000

-2000

-2000

4

Net benefits/costs

10000

5000

5000

5000

5000

5000

5

Discount factor

1

1

1

1

1

1

6

Net Present value

($10,000.00)

($5,000.00)

($5,000.00)

($5,000.00)

($5,000.00)

($5,000.00)

7

Cumulative NPV

($10,000.00)

($5,000.00)

$0.00

$5,000.00

$10,000.00

$15,000.00

From the cumulative NPV the payback period is 2 years.

Initial investment was 20,000 but year zero had a return of 10,000, meaning the effective initial investment was -10,000

Year

Cash Flow

Payback

0

-10000

1

5000

-5000

2

5000

0

3

5000

4

5000

5

5000

Initial investment was 20,000 but year zero had a return of 10,000, meaning the effective initial investment was -10,000

Year

Cash Flow

0

-10000

1

5000

2

5000

3

5000

4

5000

5

5000

Total discounted benefit amount = 25,000

Total discounted cost amount = 10000

ROI = (benefit – cost) / cost =  (25,000 – 10000)/10000 = 1.5

Therefore return on investment = 150%  

Conclusion

This report has presented an outline of a project intended to develop a Teaching and Learning System (TLS) at the Quality Institute (HQI). The report has presented a system analysis and design of the intended system. The identified functional and non-functional requirements of the proposed Teaching and Learning System (TLS) have been presented. The report has also presented a Work Breakdown Structure which identifies the various tasks required to accomplish this project. A PERT/CPM chart was developed, which outlines the critical path for the project. . The report also presented a data model of the student registration process by use of a class diagram. Finally the report presents calculations for the net present value, payback period and return on investment. From the analysis, the project is a very viable one, with a very high return on investment and a short payback period. The project should therefore continue to the implementation stage as it is feasible and viable.  

References

Burke, R. (2013). Project management: planning and control techniques. New Jersey, USA.

Dennis, A., Wixom, B. H., & Tegarden, D. (2015). Systems analysis and design: An object- oriented approach with UML. John Wiley & Sons.

Hobel, B., & Schütte, S. (2013) Work Breakdown Structure. John Wiley & Sons.

Larson, E. W., & Gray, C. (2013). Project Management: The Managerial Process with MS   Project. McGraw-Hill.