Project Management Knowledge And Skills: Analysis, Planning And Execution

Understanding Project Management Theory and its application

The work breakdown structure is developed as follows.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Figure 1: Work Breakdown Structure of the Project

(Source: Created by Author)

The network diagram of the project is developed as follows.

Save Time On Research and Writing
Hire a Pro to Write You a 100% Plagiarism-Free Paper.
Get My Paper

Figure 2: Network Diagram of the Project

(Source: Created by Author)

Figure 3: Gantt Chart of the Execution Phase (Full Gantt Chart in Appendix)

(Source: Created by Author)

The schedule for the project is developed and shown in the following table (Kerzner & Kerzner, 2017).

Task Name

Duration

Start

Finish

Predecessors

Development and Testing of a Business Website for Eagle Boys Pizza

171 days

Mon 12/3/18

Mon 7/29/19

   Project Initiation Phase

23 days

Mon 12/3/18

Wed 1/2/19

      Analysis of the Current Business State of the Restaurant

5 days

Mon 12/3/18

Fri 12/7/18

      Analysis of the Growth of Customer Base of the Restaurant

3 days

Mon 12/10/18

Wed 12/12/18

2

      Analysis of the Success of Online Food Delivery Apps in the Country

5 days

Thu 12/13/18

Wed 12/19/18

3

      Decision Regarding the Development of New Business Website

2 days

Thu 12/20/18

Fri 12/21/18

4

      Preliminary Estimations Regarding Technical Requirements

1 day

Mon 12/24/18

Mon 12/24/18

5

      Preliminary Estimations Regarding Time and Budget Required

1 day

Tue 12/25/18

Tue 12/25/18

6

      Preparation of Project Proposal

5 days

Wed 12/26/18

Tue 1/1/19

7

      Submission of Proposal to Authority

1 day

Wed 1/2/19

Wed 1/2/19

8

      Milestone 1: Approval of Project Proposal

0 days

Wed 1/2/19

Wed 1/2/19

9

   Project Preparation Phase

14 days

Thu 1/3/19

Tue 1/22/19

      Consult a Software Developer

4 days

Thu 1/3/19

Tue 1/8/19

10

      Recruit Development Team

2 days

Wed 1/9/19

Thu 1/10/19

12

      Discuss Project Requirements with the Developers

2 days

Fri 1/11/19

Mon 1/14/19

13

      Discuss the Overall Scope of the Project

2 days

Tue 1/15/19

Wed 1/16/19

14

      Discuss Development Costs

2 days

Thu 1/17/19

Fri 1/18/19

15

      Discuss Approximate Time Required to Develop the Website

1 day

Mon 1/21/19

Mon 1/21/19

16

      Finalize the Project

1 day

Tue 1/22/19

Tue 1/22/19

17

      Milestone 2: Sign Contract for the Project

0 days

Tue 1/22/19

Tue 1/22/19

18

   Project Planning Phase

16 days

Wed 1/23/19

Wed 2/13/19

      Start Preparation of the Project Plan Document

1 day

Wed 1/23/19

Wed 1/23/19

19

      Determine the Overall Scope of the Project

1 day

Thu 1/24/19

Thu 1/24/19

21

      Determine Schedule of the Project

1 day

Fri 1/25/19

Fri 1/25/19

22

      Determine Final Budget of the Project

1 day

Mon 1/28/19

Mon 1/28/19

23

      Determine Project Deliverables

2 days

Tue 1/29/19

Wed 1/30/19

24

      Determine Stakeholder Roles and Duties

1 day

Thu 1/31/19

Thu 1/31/19

25

      Develop a Suitable Communication Plan

1 day

Fri 2/1/19

Fri 2/1/19

26

      Develop a List of Hardware and Software Requirements

1 day

Mon 2/4/19

Mon 2/4/19

27

      Determine Possible Risks Associated with the Project

2 days

Tue 2/5/19

Wed 2/6/19

28

      Prepare Mitigation Plan for the Risks

3 days

Thu 2/7/19

Mon 2/11/19

29

      Finalize the Project Plan

2 days

Tue 2/12/19

Wed 2/13/19

30

      Milestone 3: Approval of Project Plan

0 days

Wed 2/13/19

Wed 2/13/19

31

   Project Execution Phase

104 days

Thu 2/14/19

Tue 7/9/19

      Purchase Hardware Required

5 days

Thu 2/14/19

Wed 2/20/19

32

      Purchase Software Required for the Website

3 days

Thu 2/21/19

Mon 2/25/19

34

      Install Website Development Platform

2 days

Tue 2/26/19

Wed 2/27/19

35

      Initiate the Development of the Website

2 days

Thu 2/28/19

Fri 3/1/19

36

      Create a Suitable Domain for the Website

5 days

Mon 3/4/19

Fri 3/8/19

37

      Develop a Sitemap for the Website

5 days

Mon 3/11/19

Fri 3/15/19

38

      Design the Wireframe of the Website

3 days

Mon 3/18/19

Wed 3/20/19

39

      Develop Website Design and Create User Interface

10 days

Thu 3/21/19

Wed 4/3/19

40

      Develop Necessary Content for the Website

6 days

Thu 4/4/19

Thu 4/11/19

41

      Assemble Layout and Contents

4 days

Fri 4/12/19

Wed 4/17/19

42

      Initiate Coding

15 days

Thu 4/18/19

Wed 5/8/19

43

      Start Testing of the Developed Website

1 day

Thu 5/9/19

Thu 5/9/19

44

      Edit and Review the Content of the Website

5 days

Fri 5/10/19

Thu 5/16/19

45

      Review and Modify Website GUI

5 days

Fri 5/17/19

Thu 5/23/19

46

      Monitor the Website Functioning and Features

4 days

Fri 5/24/19

Wed 5/29/19

47

      Detect Website Glitches and Bugs

5 days

Thu 5/30/19

Wed 6/5/19

48

      Add Patches to Solve the Bugs

2 days

Thu 6/6/19

Fri 6/7/19

49

      Monitor the Website Performance from Admin End and Client End

5 days

Mon 6/10/19

Fri 6/14/19

50

      Final Testing of the Website

10 days

Mon 6/17/19

Fri 6/28/19

51

      Review the Website Security

5 days

Mon 7/1/19

Fri 7/5/19

52

      Completion of the Development

2 days

Mon 7/8/19

Tue 7/9/19

53

      Milestone 4: Go Live

0 days

Tue 7/9/19

Tue 7/9/19

54

   Project Closing Phase

14 days

Wed 7/10/19

Mon 7/29/19

      Review the Website

1 day

Wed 7/10/19

Wed 7/10/19

55

      Appraisal of the Project

4 days

Thu 7/11/19

Tue 7/16/19

57

      Finalization of the Payments

3 days

Wed 7/17/19

Fri 7/19/19

58

      Prepare Documentation of the Project

5 days

Mon 7/22/19

Fri 7/26/19

59

      Stakeholder Signoff

1 day

Mon 7/29/19

Mon 7/29/19

60

      Milestone 5: Closing of the Project

0 days

Mon 7/29/19

Mon 7/29/19

61

For the estimation of the budget, the resource usages are shown as follows (Harrison & Lock, 2017).

Resource Name

Type

Max. Units

Std. Rate

Ovt. Rate

Project Manager

Work

100%

$150.00/hr

$0.00/hr

IT Officer

Work

100%

$115.00/hr

$0.00/hr

Finance Manager

Work

100%

$120.00/hr

$0.00/hr

HR Manager

Work

100%

$125.00/hr

$0.00/hr

Software Consultant

Work

100%

$65.00/hr

$0.00/hr

Software Developer

Work

100%

$50.00/hr

$0.00/hr

Software Tester

Work

100%

$50.00/hr

$0.00/hr

Content Creator

Work

100%

$40.00/hr

$0.00/hr

Hardware Requirements

Material

$10, 000.00

Software Requirements

Material

$4, 000.00

Accordingly, the budget is estimated using bottom up method as shown in the following table (Tyssen, Wald & Spieth, 2014).

Task Name

Resource Names

Cost

Development and Testing of a Business Website for Eagle Boys Pizza

$237, 120.00

   Project Initiation Phase

$44, 440.00

      Analysis of the Current Business State of the Restaurant

IT Officer, Project Manager

$10, 600.00

      Analysis of the Growth of Customer Base of the Restaurant

IT Officer, Project Manager, Finance Manager

$9, 240.00

      Analysis of the Success of Online Food Delivery Apps in the Country

IT Officer, Project Manager

$10, 600.00

      Decision Regarding the Development of New Business Website

IT Officer, Project Manager

$4, 240.00

      Preliminary Estimations Regarding Technical Requirements

IT Officer, Project Manager

$2, 120.00

      Preliminary Estimations Regarding Time and Budget Required

IT Officer, Project Manager

$2, 120.00

      Preparation of Project Proposal

IT Officer

$4, 600.00

      Submission of Proposal to Authority

IT Officer

$920.00

      Milestone 1: Approval of Project Proposal

Project Manager

$0.00

   Project Preparation Phase

$30, 480.00

      Consult a Software Developer

IT Officer, Project Manager, Software Consultant

$10, 560.00

      Recruit Development Team

HR Manager

$2, 000.00

      Discuss Project Requirements with the Developers

IT Officer, Software Consultant, Software Developer, Software Tester

$4, 480.00

      Discuss the Overall Scope of the Project

IT Officer, Software Consultant, Software Developer, Software Tester

$4, 480.00

      Discuss Development Costs

IT Officer, Software Consultant, Software Developer, Software Tester

$4, 480.00

      Discuss Approximate Time Required to Develop the Website

IT Officer, Software Consultant, Software Developer, Software Tester

$2, 240.00

      Finalize the Project

IT Officer, Software Consultant, Software Developer, Software Tester

$2, 240.00

      Milestone 2: Sign Contract for the Project

IT Officer, Software Consultant, Software Developer, Software Tester

$0.00

   Project Planning Phase

$46, 720.00

      Start Preparation of the Project Plan Document

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Determine the Overall Scope of the Project

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Determine Schedule of the Project

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Determine Final Budget of the Project

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Determine Project Deliverables

IT Officer, Project Manager, Software Developer, Software Tester

$5, 840.00

      Determine Stakeholder Roles and Duties

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Develop a Suitable Communication Plan

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Develop a List of Hardware and Software Requirements

IT Officer, Project Manager, Software Developer, Software Tester

$2, 920.00

      Determine Possible Risks Associated with the Project

IT Officer, Project Manager, Software Developer, Software Tester

$5, 840.00

      Prepare Mitigation Plan for the Risks

IT Officer, Project Manager, Software Developer, Software Tester

$8, 760.00

      Finalize the Project Plan

IT Officer, Project Manager, Software Developer, Software Tester

$5, 840.00

      Milestone 3: Approval of Project Plan

Project Manager

$0.00

   Project Execution Phase

$96, 560.00

      Purchase Hardware Required

Hardware Requirements[1], Software Consultant

$12, 600.00

      Purchase Software Required for the Website

Software Consultant, Software Requirements[1]

$5, 560.00

      Install Website Development Platform

Software Developer, Software Tester

$1, 600.00

      Initiate the Development of the Website

Software Developer, Software Tester

$1, 600.00

      Create a Suitable Domain for the Website

Software Developer, Software Tester

$4, 000.00

      Develop a Sitemap for the Website

Software Developer, Software Tester

$4, 000.00

      Design the Wireframe of the Website

Software Developer, Software Tester

$2, 400.00

      Develop Website Design and Create User Interface

Software Developer, Software Tester

$8, 000.00

      Develop Necessary Content for the Website

Software Developer, Software Tester

$4, 800.00

      Assemble Layout and Contents

Software Developer, Software Tester

$3, 200.00

      Initiate Coding

Software Developer, Software Tester

$12, 000.00

      Start Testing of the Developed Website

Software Developer, Software Tester

$800.00

      Edit and Review the Content of the Website

Software Developer, Software Tester, Content Creator

$5, 600.00

      Review and Modify Website GUI

Software Developer, Software Tester

$4, 000.00

      Monitor the Website Functioning and Features

Software Developer, Software Tester

$3, 200.00

      Detect Website Glitches and Bugs

Software Developer, Software Tester

$4, 000.00

      Add Patches to Solve the Bugs

Software Developer, Software Tester

$1, 600.00

      Monitor the Website Performance from Admin End and Client End

Software Developer, Software Tester

$4, 000.00

      Final Testing of the Website

Software Developer, Software Tester

$8, 000.00

      Review the Website Security

Software Developer, Software Tester

$4, 000.00

      Completion of the Development

Software Developer, Software Tester

$1, 600.00

      Milestone 4: Go Live

Software Developer, Software Tester

$0.00

   Project Closing Phase

$18, 920.00

      Review the Website

IT Officer

$920.00

      Appraisal of the Project

Project Manager

$4, 800.00

      Finalization of the Payments

Finance Manager, HR Manager

$5, 880.00

      Prepare Documentation of the Project

Content Creator

$1, 600.00

      Stakeholder Signoff

Content Creator, Finance Manager, HR Manager, IT Officer, Project Manager, Software Consultant, Software Developer, Software Tester

$5, 720.00

      Milestone 5: Closing of the Project

Project Manager

$0.00

There are a number of risks associated with the project that are listed and mitigation plan has been developed in the following risk register.

Risk Description

Chance of Occurrence

Impact on Project

Mitigation Plan

Scope creep may occur in the project due to lack of well defined project scope and project plan not aligned with the project scope and limitations

High

Medium

Definition of clear scope of the project is important; during the development of the project charter, appropriate project scope is to be developed and it is to be ensured that the stakeholders have complete understanding of the project scope

Lack of proper and specific decisions regarding the project may happen due to the presence of too many decision makers in the project team

Medium

Low

During the planning phase, an agreement should be done in order to determine who will take the majority of the main decisions throughout the course of the project (Heldman, 2018)

Due to the complexity of the required business website, some part of the coding may require a huge amount of time to achieve only some basic and marginal features of the website

High

Low

In order to address this issue, it is suggested to avoid custom coding and use basic coding to complete the website rather than waste significant amount of time on marginal features of the website

Cyber security presents a major risk in the project as external entities like malicious files, hackers and others may break the intrinsic security of the website and steal confidential information from the connected server

Very High

Extreme

It is important to protect any online hosted content using suitable software; firewalls are available to protect the computer against any external attacks while anti-virus software can help to detect and remove any virus that may enter the system through various sources (Marchewka, 2014)

While the target of the company is to develop the online food delivery website for all users, the may not be compatible with small devices like smartphones

Low

Medium

It is required to ensure the website is compatible for different platforms during the testing phase and the development must be done accordingly

The communication management plan for the stakeholders of the project is developed in the following table.

Stakeholder

Communication Purpose

Communication Frequency

Communication Medium

Project Manager

Project update, change requirements, additional requirements

Weekly

Email / Face to Face Meeting

IT Officer

IT requirements of the system, system requirements and updates regarding project

Daily

Face to Face

Finance Manager

Manage finances and budget of the project

As required

Finance sheets, expenditure report

HR Manager

Human resource requirements, payment of wages

As required

Email

Software Consultant

System and project requirements

During project planning

Face to Face

Software Developer

System and project requirements

During project planning

Face to Face

Software Tester

System and project requirements

During project planning

Face to Face

Content Creator

System content requirements

During project planning

Face to Face

The main deliverable of the project is the new business website for Eagle Boys Pizza. The status report for the execution phase is shown in the following table.

Task Name

Status

Expected Performance Against Schedule

Budget

Purchase Hardware Required

PENDING

+2 days

+$2500

Purchase Software Required for the Website

PENDING

Ok

+$1000

Install Website Development Platform

PENDING

+1 day

Initiate the Development of the Website

PENDING

Ok

Create a Suitable Domain for the Website

PENDING

+2 days

Develop a Sitemap for the Website

PENDING

+2 days

Design the Wireframe of the Website

PENDING

-1 day

Develop Website Design and Create User Interface

PENDING

-2 days

Develop Necessary Content for the Website

PENDING

+/- 1 day

Assemble Layout and Contents

PENDING

+3 days

Initiate Coding

PENDING

Ok

Start Testing of the Developed Website

PENDING

Ok

Edit and Review the Content of the Website

PENDING

+1 day

Review and Modify Website GUI

PENDING

+4 days

Monitor the Website Functioning and Features

PENDING

+2 days

Detect Website Glitches and Bugs

PENDING

+5 days

Add Patches to Solve the Bugs

PENDING

+2 days

Monitor the Website Performance from Admin End and Client End

PENDING

+2 days

Final Testing of the Website

PENDING

Ok

Review the Website Security

PENDING

Ok

Completion of the Development

PENDING

Ok

This project has been based on estimated variables and attributes. Based on the requirements of the business website development, the appropriate activities have been listed and accordingly the schedule has been developed. Furthermore, based on the allocation of resources, the project budget has been accordingly determined.

From this project plan, I have learnt the use of various tools and techniques of project management that helps one to analyze the case presented and develop a plan accordingly. I also learnt about the main attributes of a project management plan and the method of accurate estimation of time and budget.

References

Aga, D. A., Noorderhaven, N., & Vallejo, B. (2016). Transformational leadership and project success: The mediating role of team-building. International Journal of Project Management, 34(5), 806-818.

Binder, J. (2016). Global project management: communication, collaboration and management across borders. Routledge.

Burke, R., & Barron, S. (2014). Project management leadership: building creative teams. John Wiley & Sons.

Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014). Can agile project management be adopted by industries other than software development?. Project Management Journal, 45(3), 21-34.

Crawford, J. K. (2014). Project management maturity model. Auerbach Publications.

Harrison, F., & Lock, D. (2017). Advanced project management: a structured approach. Routledge.

Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley & Sons.

Kerzner, H., & Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kilibarda, G. D., Šobaji?, V. M., Beri?, I. M., & Jovanovi?, P. M. (2016). Software project management. Tehnika, 71(1), 145-152.

Kundra, T., & Sharma, A. (2015). Software project management. Int. J. Res.

Lee, M. R. (2016). Leading virtual project teams: Adapting leadership theories and communications techniques to 21st century organizations. Auerbach Publications.

Marchewka, J. T. (2014). Information technology project management. John Wiley & Sons.

Niazi, M., Mahmood, S., Alshayeb, M., Qureshi, A. M., Faisal, K., & Cerpa, N. (2016). Toward successful project management in global software development. International Journal of Project Management, 34(8), 1553-1567.

Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great: The benefits of investment in project management training and education. International Journal of Project Management, 33(1), 41-52.

Redick, A., Reyna, I., Schaffer, C., & Toomey, D. (2014). Four-factor model for effective project leadership competency. Journal of Information Technology and Economic Development, 5(1), 53.

Schwalbe, K. (2015). Information technology project management. Cengage Learning.

Silva, P., Moreno, A. M., & Peters, L. (2015). Software Project Management: Learning from Our Mistakes. IEEE Software, (3), 40-43.

Trendowicz, A., & Jeffery, R. (2014). Software project effort estimation. Foundations and Best Practice Guidelines for Success, Constructive Cost Model–COCOMO pags, 277-293.

Tyssen, A. K., Wald, A., & Spieth, P. (2014). The challenge of transactional and transformational leadership in projects. International Journal of Project Management, 32(3), 365-375.

Walker, A. (2015). Project management in construction. John Wiley & Sons.